Submission Date | Project Number | Project Name | Contractor | Base Bid | Alternates | Notice of Intent Issued |
---|---|---|---|---|---|---|
12-21-18 | 18600 | Replace Remaining Fan Coil Units, Idaho Division of Veterans Services, Boise, Idaho | ||||
Hobson Fabricating Corp. | $440,400 | 1. $77,200 2. $66,600 3. $66,600 Unit Price: N/A |
||||
Acco Engineered Systems. | $345,751 | 1. $63,042 2. $50,831 3. $50,272 Unit Price: $5,534 |
01/08/19 | |||
TVR | $363,499 | 1. $77,510 2. $62,374 3. $60,787 Unit Price: $5,959 |
||||
Cascade Enterprises | $615,000 | 1. $135,000 2. $135,000 3. $135,000 Unit Price: $615,000 |
10-23-18 | 18332 | Alteration & Repair Bldg. 901, Gowen, Division of Military, Boise, Idaho | |
Winspear Construction | $299,500 | 1. $8,200 2. $15,200 3. $10,900 4. $91,100 5. $85,000 |
||||
Hamilton Builders | $265,500 | 1. $8,500 2. $14,700 3. $8,700 4. $20,500 5. $33,300 |
||||
Bricon, Inc. | $189,900 | 1. $7,400 2. $13,000 3. $7,000 4. $45,000 5. $77,000 |
||||
Triple G Construction NON-RESPONSIVE |
||||||
Wright Brothers | $184,657 | 1. $5,540 2. $12,450 3. $5,660 4. $13,040 5. $63,100 |
11-08-18 | |||
Excelsior NON-RESPONSIVE |
10-23-18 | 18066 REBID | Remodel Community Re-Entry Center Restrooms, Department of Correction, Idaho Falls, Idaho | |||
Advanced Fuel Systems | $93,300 | 1. $87,900 | 11-06-18 | |||
Big-D | $103,808 | 1. $90,106 | ||||
BFC Diversified | $111,653 | 1. $92,208 | ||||
J&S Construction | $139,795 | 1. $119,422 | ||||
Rivers West Construction | $155,875 | 1. $125,624 | CR Clark | $159,400 | 1. $126,200 | 10-18-18 | 17352 | Front Entry Retaining Wall, State Health Lab, Department of Health & Welfare, Boise, Idaho |
Precision Grading & Excavation | $246,213 | |||||
Clearwater Landscape | $105,721 | 10-26-18 | ||||
Bri Con, Inc. | $185,000 | |||||
Hellmann Construction | $167,998 | |||||
Excelsior Construction | $141,950 | 10-10-18 | 18060 – Rebid | Replace Roof, Wright Hall, Kitchen/Dining Area, South Idaho correctional Institution (SICI), Dept. of Correction, Kuna, Idaho | ||
Upson Company. | $256,397 | 1. $6,111 2. $36,000 3. $74,600 4. $81,200 Unit Price: $13,900 |
||||
Nations Roof Mtn. | $229,345 | 1. $6,200 2. $14,000 3. $69,800 4. $5,600 Unit Price: $500.00 |
10/22/18 | |||
Quality Tile Roofing | $309,766 | 1. $2,086 2. $19,133 3. $84,932 4. $1,554 Unit Price: $8,600 |
||||
Signature Roofing | $267,000 | 1. $8,273 2. $21,000 3. $57,737 4. $4,340 Unit Price: $9,800 |
09-20-18 | 18601 | Replace Windows, Division of Veterans Services, Pocatello, Idaho | |
Western Design | $128,544.57 | 1.$29,003.62 | 10-11-18 | |||
Precision Glass | $145,637 | 1. $85,800 |
||||
08-16-18 | 18334 | Roof Overbuild, Idaho Youth Challenge Academy, Division of Military, Pierce, Idaho Bid is Rejected |
||||
Wright Brother’s | ||||||
08-09-18 | 18333 | Upgrade Compound Parking, Lighting, and Storage, Burley Readiness Center, Division of Military, Burley, Idaho | ||||
DePatco, Inc. | $290,759 | 1. $10,477 | ||||
PBC Petersen Brothers | $260,000 | 1. $5,000 |
08-30-18 | |||
RC Heavy Haul | $264,134 | 1. $28,530 |
||||
Starr Corp. | $258,000 | 1. $10,000 |
||||
08-09-18 | 18330 | Parking Lot and Storage, Blackfoot Readiness Center, Division of Military, Blackfoot, Idaho | ||||
DePatco, Inc. | $260,446 | |||||
J&S Construction | $410,783 | |||||
RC Heavy Haul | $229,010 | |||||
Starr Corp. | $199,000 | 08-30-18 | ||||
08-09-18 | 18061 | (RE-BID) Replace HVAC North Dorm, SICI, Idaho Department of Correction, Kuna, Idaho | ||||
YMC, Inc. | $275,419 | 1. $75,000 | ||||
Acco Engineered Systems | $319,457 | 1. $62,053 |
||||
American Chiller Service | $181,269 | 1. $49,430 |
08-07-18 | 16061 | Waste Water Upgrades, Phase 2, NICI, Idaho Department of Correction, Cottonwood, Idaho | |
McMillen, LLC. | $2,299,007 | 1. $59,620 2. $48,370 3. $326,970 4. $40,470 |
08/24/18 | |||
S & L Underground | $2,784,200 | 1. $85,000 2. $74,000 3. $422,000 4. $110,000 |
||||
Syblon Reid | $2,830,000 | 1. $125,000 2. $60,000 3. $395,000 4. $40,000 |
||||
Cascade Enterprises | $2,750,000 | 1. $87,000 2. $68,000 3. $396,000 4. $75,700 |
||||
08-06-18 | 17239 | Replace Chillers, Oboler Library, Idaho State University, Pocatello, Idaho | ||||
CR Clark | $645,000 | 1. $50,336 2. $13,500 |
||||
B & S Boiler | $567,000 | 1. $36,500 2. $11,250 |
08-31-18 | |||
08-02-18 | 18602B | Fire Suppression for IT Rooms, Division of Veteran Services, Boise, Idaho | ||||
Pacific Source Construction | $103,803 | 1. $81,500 2. $39,500 3. $25,500 |
||||
Johnson Controls | $45,995 | 1. $38,850 2. $28,900 3. $14,910 | 07-18-18 | 18191 | BSU Lab Space Renovation, MPC Building, Boise State University, Boise, Idaho * ALL BIDS REJECTED* |
|
HC Company | ||||||
Wright Brothers | ||||||
Perkins Construction | ||||||
Excelsior Construction | ||||||
Petra | ||||||
07-17-18 | 18170 | Construct Permanent Parking Lot, Educational Corridor, North Idaho College, Coeur d’Alene, Idaho | ||||
T. LaRiviere Equipment & Excavation | $1,197,601 | 1. $45,371 2. $330,430 |
||||
Ginno Construction | $676,700 | 1. $39,120 2. $1,756 |
07-27-18 | |||
07-17-18 | 16130 | Repair Parking Lot, Eastern Idaho Technical College, Idaho Falls, Idaho | ||||
R.C. Heavy Haul NON-RESPONSIVE |
||||||
TMC Construction | $192,945 | 1. $37,645 2. $12,716 3. $20,690 |
||||
Thompson Paving | $150,412.50 | 1. $9,344.50 2. $16,896 3. $19,586.60 |
08-22-18 | |||
07-16-18 | 15720 | Road Repairs, Old Penitentiary Road, Idaho State Historical Society, Boise, Idaho * ALL BIDS REJECTED* |
||||
Blue Sky Construction | ||||||
Diamond Contractors | ||||||
Knife River Corporation | ||||||
06-28-18 | 18602L | Fire Suppression for IT Rooms, Division of Veteran Services, Lewiston, Idaho |
||||
K & G Construction | $59,800 | 07-19-18 | ||||
06-28-18 | 18602P | Fire Suppression for IT Rooms, Division of Veteran Services, Pocatello, Idaho NO BIDS RECEIVED |
||||
06-26-18 | 17610 | (REBID) Re-Seal Parking Lot, Division of Veterans Services, Boise, Idaho | ||||
Top Job, LLC. | $63,463 | 1. $7,379 2. $1,995 3. $28,326 |
||||
Young Paving, Inc. | $42,000 | 1. $6,400 2. $4,600 3. $26,000 |
06-28-18 | |||
06-19-18 | 17131 | Security Measure Upgrades, Access Control System, Phase II, Eastern Idaho Technical College, Idaho Falls, Idaho | ||||
System Tech | $88,897 | 1. $8,779 2. $25,767 |
06-22-18 | |||
06-19-18 | 18090 | LED Upgrade, Walkway Lights, College of Southern Idaho, Twin Falls, Idaho | ||||
Gietzen Electric | $159,874 | 1. $20,330 2. $5,126 3. $4,309 Unit Price $ 50 |
||||
Heglar Creek Electric | $149,000 | 1. $20,800 2. $5,400 3. $2,800 Unit Price $ 22 |
07/05/18 | |||
06-14-18 | 18066 | Remodel Community Re-Entry Center Restrooms, Department of Correction, Idaho Falls, Idaho NO BIDS RECEIVED |
||||
06-13-18 | 18060 | Replace Roof, Wright Hall, Kitchen/Dining Area, Department of Correction (SICI), Kuna, Idaho *ALL BIDS REJECTED* |
||||
Upson Company | ||||||
Pro Tech Roofing, Inc. |
|
|||||
Signature Roofing | ||||||
06-07-18 | 17612 | Replace Liquid Oxygen Tank – VETL, Division of Veterans Services, Lewiston, Idaho | ||||
K & G Construction | $170,944 | 6-29-18 | ||||
NNAC | $206,439 | |||||
06-07-18 | 18110 | (REBID) New HVAC, Cottages and Infirmary, Idaho Educational Services for the Deaf and Blind, Gooding, Idaho | ||||
RM Mecanical | $281,196 | 1. $12,100 | ||||
Western Heating & Air | $305,427 | 1. $28,750 |
||||
Element Heating & Air | $277,870 | 1. $16,870 |
||||
TVR | $248,649 | 1. $5,479 |
06-21-18 | |||
05-31-18 | 18150 | Upgrade HVAC, Sam Glenn Complex, Lewis-Clark State College, Lewiston, Idaho NO BIDS RECEIVED |
||||
05-30-18 | 18258 | Lionel Hampton School of Music Building Restroom and Entrance Accessibility Renovations, University of Idaho, Moscow, Idaho. *ALL BIDS REJECTED* |
||||
Ginno Construction | ||||||
05-29-18 | 17610 | Reseal Parking Lot, Division of Veterans Services, Boise, Idaho | ||||
Top Job LLC NON-RESPONSIVE |
||||||
05-24-18 | 18256 | Improvements/Expansion, WWAMI Medical Education Builidng, University of Idaho | ||||
Quality Contractors | $3,055,000 | 1. $450,000 2. $189,000 3. $170,000 4. $105,000 |
06-18-18 | |||
Ginno Construction | $3,180,000 | 1. $430,000 2. $135,000 3. $150,000 4. $60,000 |
||||
05-17-18 | 17234 | Remodel Infrastructures, Gale Life Science Bldg. #65, Phase I, Idaho State University, Pocatello, Idaho | ||||
Ormond Builder | $364,710 | |||||
Harper Construction | $495,000 | |||||
Western Design | $534,800 | |||||
Starr Corp. | $300,000 | 05-22-18 | ||||
05-17-18 | 17222 | Remodel Program Space, PT/OT, Garrison Hall, Idaho State University, Pocatello, Idaho | ||||
BFC Diversified | $201,204 | |||||
Construction Services | $194,509 | |||||
Western Design | $179,900 | 05-30-18 | ||||
05-16-18 | 16229 | ADA Elevator, ESTEC Bldg. #49, Idaho State University, Pocatello, Idaho | ||||
CR Clark Construction | $295,500 | 05-23-18 | ||||
Western Design | $239,982 | |||||
05-15-18 | 18854 | (REBID) Asbestos Abatement Service Contract – Southeast Idaho | ||||
Idaho Abatement | $71,720 | |||||
PTI | $47,600 | 05-22-18 | ||||
Abatement Pro | $48,800 | |||||
05-15-18 | 18221 | Replace Chiller, COE, Idaho State University, Pocatello, Idaho | ||||
Lewis Corp | $207,700 | 1. $32,950 2. $28,100 3. $25,200 |
||||
B & S Boiler | $205,000 | 1. $25,000 2. $32,250 3. $17,500 |
||||
ACS | $187,560 | 1. $17,793 2. $18,576 3. $19,524 |
||||
Mech Solutions | $179,000 | 1. $14,250 2. $19,250 3. $12,500 |
05-30-18 | |||
05-15-18 | 18110 | New HVAC, Cottages and Infirmary, Idaho Educational Services for the Deaf and Blind |
||||
Western Heating & Air NON-RESPONSIVE |
||||||
05-10-18 | 18061 | Replace HVAC North Dorm, SICI, Department of Correction, Kuna, Idaho | ||||
Acco Engineered Systems NON-RESPONSIVE |
05-10-18 | 18224 | Replace Chiller, Fine Arts Building, Idaho State University, Pocatello, Idaho NO BIDS RECEIVED |
|||
05-08-18 | 18092 | Canyon Entryway Replacement, College of Southern Idaho, Twin Falls, Idaho | ||||
Starr Corporation | $69,000 | 1. $140,000 | 05-30-18 | 05-08-18 | 18621 | ADA Upgrades, Idaho History Center, Idaho State Historical Society, Boise, Idaho |
Excelsior Construction | $99,500 | |||||
Gafford Construction | $98,625 | 05-22-18 | 05-03-18 | 18202 | Games Center Restroom Renovation, Student Union Building, Boise State University, Boise, Idaho | |
Excelsior Construction Co. | $199,200 | 1. $29,900 | 06-04-18 | |||
05-03-18 | 18533 | Roof & Concrete Repair, Owyhee Cottage, JCC, Department of Correction, St. Anthony Idaho | ||||
CR Clark Construction | $224,800 | 1. $48,700 | 05-11-18 | |||
DL Beck | $249,762.68 | 1. $35,078 |
||||
J&S Construction | $273,130 | 1. $50,580 |
||||
04-24-18 | 17193 | Chiller Replacement, Engineering Building, Boise State University, Boise, Idaho | ||||
American Chiller Service | $128,374 | 1. $4,786 | ||||
Cascade Enterprises | $135,000 | 1. $5,000 |
||||
Lacy Mechanical | $139,600 | 1. $6,400 |
||||
TVR | $119,175 | 1. $4,265 |
||||
Acco Engineered Systems | $103,640 | 1. $5,777 |
04-30-18 | |||
YMC, Inc. | $159,840 | 1. $11,594 |
||||
04-19-18 | 18862 | Elevator Service, Maintenance, Alteration, and Repairs Contract, Chinden Campus, Boise, Idaho | ||||
ThyssenKrupp Elevator | $107,932 | |||||
Schindler Elevator Corp. | $95,260 | 04-24-18 | 04-13-18 | 18195 | CID Renovations and Stack Relocation, Albertsons Library, Boise State University, Boise, Idaho | |
Perkins Construction, Inc. | $240,185 | 1. $82,125 | ||||
Gafford Construction, Inc. | $236,641 | 1. $43,977 |
||||
Pacific Source Construction | $267,000 | 1. $82,000 |
||||
Excelsior Construction Co. | $227,500 | 1. $34,500 |
04-24-18 | 04-12-18 | 18861 | Elevator Service, Maintenance, Alteration, and Repairs Contract, Capitol Mall, Boise, Idaho |
Otis Elevator Co. | $291,370 | |||||
Schindler Elevator Corp. | $189,090 | |||||
ThyssenKrupp Elevator | $147,260 | 04-17-18 | 04-12-18 | 18863 | Elevator Service, Maintenance, Alteration, and Repairs Contract, Idaho Falls | |
ThyssenKrupp Elevator | $14,880 | 04-17-18 | ||||
Schindler Elevator Corp. | $20,020 | 04-12-18 | 18864 | Elevator Service, Maintenance, Alteration, and Repairs Contract, Lewiston, Idaho | ||
ThyssenKrupp Elevator | $27,375 | |||||
Schindler Elevator Corp. | $21,110 | 04-17-18 | 04-10-18 | 18131 | Remodel Light Diesel & Welding Shop, Eastern Idaho Technical College, Idaho Falls, Idaho | |
Alan Clark Construction | $145,800 | 1. $8,900 | ||||
BFC Diversified | $136,299 | 1. $7,935 |
4-17-18 | |||
CR Clark Construction | $155,572 | 1. $16,600 |
||||
J & S Construction | $154,337 | 1. $11,704 |
||||
Petra Inc. | $190,077 | 1. $8,381 |
||||
Western Design | $144,890 | 1. $11,500 |
||||
04-10-18 | 16223 | (REBID) Masonry Repairs, Campus Wide, Idaho State University, Idaho | ||||
IMS Masonry | $197,547 | |||||
Hydro-Tech | $169,500 | 05-03-18 | ||||
CR Clark | $221,300 | |||||
Western Design | $158,998 | 04-10-18 | 18223 | Replace Chiller, Liberal Arts, Idaho State University, Pocatello, Idaho | ||
Big-D Construction NON-RESPONSIVE |
||||||
CR Clark Construction | $166,900 | 1. $15,000 2. $15,000 3. $900 |
04-27-18 | |||
Industrial Construction | $188,800 | 1. $10,220 2. $15,017 3. $934 |
||||
04-03-18 | 18220 | Ventilation & Controls, Health Code Compliance, 2nd Floor Restrooms, Oboler Library, Idaho State University, Pocatello, Idaho | ||||
BFC Diversified | $161,292 | 1. $11,000 2. $11,000 |
04-16-18 | |||
CR Clark Construction | $272,800 | 1. $6,800 2. $6,800 |
||||
Western Design | $198,952 | 1. $4,295 2. $4,295 |
||||
03-9-18 | 16251 | North Idaho Collaborative Classroom Building, Coeur d’Alene, Idaho | ||||
Northcon Inc. | $7,650,000 | 1. $114,700 2. $15,000 3. $39,200 4. $27,900 5. $32,200 6. $32,200 Unit Price $8.75 |
||||
Ginno Construction | $7,215,000 | 1. $99,800 2. $11,500 3. $37,800 4. $41,500 5. $48,000 6. $49,000 Unit Price $22.00 |
03-19-18 |
|||
Meridian Construction NON-RESPONSIVE |
||||||
TW Clark | $7,548,000 | 1. $110,000 2. $4,700 3. $38,000 4. $27,000 5. $52,000 6. $49,000 Unit Price $40.00 |
||||
Bouten Construction | $7,570,000 | 1. $95,900 2. $5,000 3. $37,500 4. $26,700 5. $31,000 6. $31,000 Unit Price $40.00 |
||||
Walker Construction | $7,290,000 | 1. $127,000 2. $24,000 3. $37,000 4. $41,000 5. $32,000 6. $29,000 Unit Price $36.80 |
03-06-18 | 17359 | Protective Finishes – PTF Building, State Hospital South, Department of Health and Welfare, Blackfoot, Idaho | |
BFC Diversified | $292,503 | 1. $5,750 | ||||
CR Clark Construction | $273,300 | 1. $12,300 | ||||
Harper Construction | $259,000 | 1. $15,250 | ||||
Harris Inc. NON-RESPONSIVE |
||||||
Industrial Construction, Inc. | $263,440 | 1. $6,684 | 03-19-18 | |||
Western Design, LLC NON-RESPONSIVE |
Eagle Rock Timber | $269,784 | 1. $16,241 | |||
03-01-18 | 18254 | Chiller #4 Relocation, University of Idaho, Moscow, Idaho | ||||
Shannon Ind. Cont. | $279,000 | 1. $30,200 2. $62,000 |
||||
McCintock & Turk Inc. | $255,000 | 1. $28,330 2. $64,385 |
03-21-18 | |||
Quality Contractors | $321,800 | 1. $53,000 2. $68,400 |
||||
03-01-18 | 18250 | Carpet Replacement Corridors, TLC, University of Idaho, Moscow, Idaho | ||||
NNAC | $309,917 | 1. $31,137 2. $3,153 3. $6,706 |
||||
WM Welch Corp. | $265,569 | 1. $19,550 2. $4,690 3. $6,596 |
03-15-18 | |||
Quality Contractors | $298,000 | 1. $32,900 2. $5,300 3. $8,900 |
||||
03-01-18 | 17153 | (REBID) Conference Center Folding Partitions, Lewis-Clark State College, Lewiston, Idaho | ||||
NNAC | $337,540 | |||||
Skinner Steel | $180,976.77 | 03-20-18 | ||||
Kenaston Corp. | $229,879 | |||||
02-08-18 | 16380 | Replace Fire Alarm System, State Hospital North, Department of Health and Welfare, Orofino, Idaho | ||||
Mike’s Mechanical | $163,000 | 02-21-18 | ||||
Strom Electric | $290,000 | 01-30-18 | 18361 | Replace 140-Ton Cooling System, Idaho Department of Health and Welfare, State Hospital South, Administration Building, Blackfoot, Idaho | ||
YMC, Inc. | $178,800 | 1. $12,400 | ||||
American Chiller Service | $145,055 | 1. $ 5,867 | 02-05-18 | |||
Lewis Corporation | $164,000 | 1. $10,850 | ||||
01-16-18 | 17110 | Upgrade Irrigation System, Idaho Educational Services for the Deaf and Blind, Gooding, Idaho | ||||
Cutting Edge Landscape | $ 264,239 | 1. $19,300 2. $ 1,825 3. $20,300 |
||||
Clearwater Landscaping | $ 267,617 | 1. $11,195 2. $ 2,144 3. $10,312 |
||||
Franz Witte | $ 224,950 | 1. $24,000 2. $ 9,000 3. $26,000 |
02-08-18 | |||
Windsors, Inc. NON-RESPONSIVE |
||||||
01-23-18 | 17351 | Remodel Patient Unit Four Observation Area, State Hospital North, Department of Health and Welfare, Orofino, Idaho | ||||
NNAC | $482,000 | 1. $104,460 2. $93,000 |
||||
Mangum | $390,000 | 1. $130,443 2. $119,500 |
02-09-18 | |||
Quality | $498,000 | 1. $159,000 2. $147,000 |
01-16-18 | 12190 | Storm Water Drainage System, Phase 6, Boise State University, Boise, Idaho | |
Blue Sky Construction, LLC | $251,370 | |||||
Jim Buffington Construction | $172,702 | 01-23-18 | ||||
Granite Excavation | $285,762 | |||||
Anderson & Wood Construction Co. | $299,015 | |||||
Paul Construction | $285,000 | |||||
01-16-18 | 18852 & 18853 | Asbestos Abatement Service Contracts (2) – South West Idaho | ||||
AbatementPro | $ 47,800 | 01-22-18 | ||||
Pacific Technologies, Inc. | $ 47,195 | 01-22-18 | ||||
Northwest Technologies, Inc. | $ 84,200 | |||||
Ideal Demolition Services | $ 66,470 | 01-16-18 | 18854 | Asbestos Abatement Service Contract – South East Idaho NO BIDS RECEIVED |
||
01-16-18 | 18855 | Asbestos Abatement Service Contract – North Idaho | ||||
Specialty Environmental | $120,600 | |||||
Summit Environmental Group, Inc. | $ 70,899 | 01-22-18 |